Commercial Case Study · Tunbridge Wells
Keady Construction Commercial Mirror Package
Oversized gym mirrors, changing-room mirrors and bespoke bronze bar mirrors delivered under a demanding handover programme.
View ProjectProject Overview
A Programme-Critical Commercial Mirror Package
CreoGlass was appointed by Keady Procurement to complete a package of bespoke mirrors for a new development in Tunbridge Wells. The initial requirement focused on the basement gym, where a large-format mirror wall had to be surveyed, manufactured and installed within an approximately two-week programme.
The scope later expanded to include mirrors for ground-floor changing rooms and washrooms, followed by an urgent request for bronze mirrors within the restaurant and bar areas immediately before handover.
The gym installation required precise coordination around ballet-bar brackets that had already been fixed to the wall. Each mirror panel was individually measured and manufactured with minimal notch cut-outs, allowing the stainless-steel support fins to align with the mirror joints while preserving a clean, continuous appearance.
Project Gallery
From Survey to Final Installation
The installation included oversized gym mirrors, changing room mirrors, washroom mirrors and bespoke bronze mirrors completed under a demanding construction programme.
Technical Highlights
Precision Installation Under Programme Pressure
Delivering the project required more than manufacturing large mirrors. Existing fittings, limited tolerances and an accelerated construction programme demanded careful surveying, precise CNC machining and experienced installation.
Oversized Mirror Panels
The gym mirrors were manufactured in large formats to minimise visible joints while creating a clean, uninterrupted reflective wall suitable for a commercial fitness environment.
Precision CNC Notching
Stainless-steel ballet bar brackets had already been installed before the mirrors were measured. Every panel required bespoke CNC cut-outs with carefully calculated tolerances to achieve a precise fit around each support.
Installation Sequencing
Large, heavy mirror panels had to be manoeuvred between existing wall-mounted brackets without damaging either the mirrors or completed finishes. Careful installation planning ensured each panel could be positioned safely.
Rapid Project Delivery
Following completion of the gym mirrors, additional bronze mirrors were requested for the restaurant and bar shortly before handover. Survey, manufacture and installation were completed in approximately two days, helping the contractor maintain programme.
Scope of Works
Complete Commercial Mirror Package
CreoGlass supplied, manufactured and installed a range of bespoke mirrors throughout the development, supporting the contractor with both planned works and additional requirements introduced shortly before project completion.
Commercial Survey
Full site survey and digital measurement of all mirror locations.
Gym Mirror Wall
Oversized bespoke mirror panels with precision-machined cut-outs around existing ballet bar supports.
Changing Rooms
Custom mirrors manufactured to suit the completed interior fit-out.
Washrooms
Bespoke mirrors supplied and installed throughout the communal facilities.
Bronze Bar Mirrors
Manufacture and installation of bronze mirrors completed within approximately 48 hours before handover.
Installation
Carefully coordinated installation to minimise disruption while meeting the contractor's programme.
Project Outcome
Delivered on Programme Without Compromising Quality
The completed installation provides a clean, contemporary finish throughout the development while meeting the demanding programme expected by the main contractor. Large-format gym mirrors create a seamless training environment, while bespoke bronze mirrors add warmth and character to the completed restaurant and bar.
By combining accurate surveying, precision manufacturing and experienced installation, CreoGlass was able to accommodate existing site conditions without compromising the finished appearance. Every mirror was manufactured specifically for its location, ensuring consistent joints, accurate alignment and a professional finish across the project.
The ability to respond quickly to additional client requirements—including surveying, manufacturing and installing bespoke bronze mirrors within approximately 48 hours—demonstrated the flexibility required on fast-moving commercial construction projects. The development was completed on schedule, and the successful delivery has strengthened CreoGlass' ongoing relationship with Keady Construction for future commercial projects.
Similar Projects
From commercial gyms and hospitality venues to luxury residential developments, CreoGlass works with contractors, architects and interior designers to deliver bespoke mirror and architectural glass installations across the UK.
Looking for a Specialist Commercial Glass Partner?
Delivered on Programme Without Compromising Quality
The completed installation provides a clean, contemporary finish throughout the development while meeting the demanding programme expected by the main contractor. Large-format gym mirrors create a seamless training environment, while bespoke bronze mirrors add warmth and character to the completed restaurant and bar.
By combining accurate surveying, precision manufacturing and experienced installation, CreoGlass was able to accommodate existing site conditions without compromising the finished appearance. Every mirror was manufactured specifically for its location, ensuring consistent joints, accurate alignment and a professional finish across the project.
The ability to respond quickly to additional client requirements—including surveying, manufacturing and installing bespoke bronze mirrors within approximately 48 hours—demonstrated the flexibility required on fast-moving commercial construction projects. The development was completed on schedule, and the successful delivery has strengthened CreoGlass' ongoing relationship with Keady Construction for future commercial projects.