Government of Jersey Headquarters in St Helier

Commercial Mirror Installation · St Helier, Jersey

Government of Jersey Headquarters

Manufacture, supply and installation of 160 bespoke impact-resistant mirrors across 80 washroom facilities and seven floors.

160 Safety Mirrors
80 Washrooms
7 Floors
2.5t Glass Delivered

Project Overview

Large-Scale Commercial Mirror Installation for a Landmark Government Building

CreoGlass was contracted to manufacture, supply and install 160 bespoke impact-resistant mirrors for the new Government of Jersey Headquarters in St Helier.

The mirrors were distributed across approximately 80 washroom facilities over seven floors. Each mirror required accurate surveying, templating, manufacturing, protective packaging and coordinated installation within a demanding commercial construction programme.

Although the mirror specification was relatively straightforward, the project became highly complex because of its location. Transporting more than 2.5 tonnes of glass to Jersey required ferry coordination, detailed load planning, customs documentation, site access approval and careful consideration of local working restrictions.

With replacement glass requiring another mainland manufacture and ferry delivery, accuracy was critical. Every unit had to arrive safely, correspond to its intended location and be installed correctly first time.

Logistics & Project Delivery

Moving 2.5 Tonnes of Bespoke Glass to an Island Site

The technical specification was only one part of the project. The greater challenge was transporting, distributing and installing 160 individually prepared mirrors in Jersey within a tightly controlled programme.

01

Qualification and Compliance

Before mobilisation, the project required an extensive contractor qualification process covering the nature of the works, workforce permissions, declared load value, materials, taxation and transport limitations.

02

Ferry Transport

All mirrors were packed and loaded for ferry transport to St Helier. Weight limits, load security, sailing times and site delivery windows had to be coordinated before the installation team travelled.

03

Rapid Manual Off-Load

Parking and unloading restrictions meant approximately 2.5 tonnes of glass had to be removed from the vehicle quickly and safely. The work was completed under significant time pressure and strict site controls.

04

No Operational Lift

With no working goods lift available, the mirrors had to be manually distributed throughout the building and carried to their allocated locations across seven floors.

05

Zero Margin for Error

Every mirror had been individually surveyed and assigned to a specific room. Any measurement, manufacturing or handling error would have required another mainland production cycle and ferry delivery.

06

Two-Day Installation

The installation team worked approximately 12 hours per day to complete the programme within two days while maintaining strict health and safety standards throughout.

The project demanded accurate surveying, disciplined load planning, careful manual handling and constant coordination with the principal contractor. Every mirror was delivered and installed within the agreed programme.

Project Scale

A Commercial Mirror Package Delivered Under Intensive Site Conditions

The success of the project depended on accurate surveying, disciplined manufacturing, secure transport and carefully coordinated installation. Every mirror had to reach its allocated washroom safely and fit correctly first time.

160 Impact-Resistant Mirrors
80 Washroom Facilities
7 Building Floors
2.5t Approximate Glass Load
2 Days Installation Programme
12 hrs Worked Per Installation Day
01

Individual Surveying

All 160 mirror locations were measured and recorded before manufacture, reducing installation risk and ensuring each unit corresponded with its intended washroom.

02

Impact-Resistant Specification

The mirrors were produced for high-use commercial washroom environments where safety, durability and secure fixing were essential requirements.

03

Controlled Packaging

The complete mirror package was prepared for long-distance road and ferry transport, with protective separation and load planning to minimise the risk of movement or damage.

04

Manual Floor Distribution

With no operational goods lift available, the installation team manually carried and distributed the glass throughout all seven floors before fitting commenced.

Challenges & Solution

Successful Delivery With No Practical Margin for Error

The Challenge

A large mirror package separated from the mainland by significant logistical and commercial risk.

The installation involved far more than transporting glass to a conventional construction site. The complete package had to be surveyed, manufactured, documented, packed and transported to Jersey before being manually distributed throughout a seven-storey building.

Ferry schedules, customs and tax requirements, vehicle load limitations, site access restrictions and strict health and safety procedures all had to be addressed before installation could begin.

Once on site, the absence of an operational goods lift required the team to manually carry approximately 2.5 tonnes of glass to the relevant floors.

The CreoGlass Solution

Detailed preparation, controlled manufacturing and disciplined installation planning.

Every mirror location was surveyed and recorded before production. The mirrors were manufactured as an individually coordinated package, clearly allocated to their intended washrooms and packed for road and ferry transport.

On arrival in St Helier, the team organised a rapid manual off-load before distributing the mirrors throughout the building. Installation was then completed over two intensive working days while complying with the principal contractor’s site procedures.

Careful preparation reduced the risk of damaged, misplaced or incorrectly sized units and enabled the full package to be completed within programme.

Finished Result

A Complete Commercial Mirror Package Delivered Across Seven Floors

CreoGlass successfully completed the manufacture, supply and installation of all 160 impact-resistant mirrors for the new Government of Jersey Headquarters.

The project demonstrates our ability to manage commercial glass packages where logistics, contractor compliance, accurate surveying and installation planning are as important as the finished product.

For architects, developers and main contractors, it provides clear evidence that CreoGlass can support large, multi-floor developments throughout the UK and Channel Islands.

“Every unit had to be surveyed, manufactured, transported and installed correctly first time. The distance and replacement cost left virtually no room for error.”